How do I know if a job made money in a home service business?

By the Truceipts team · Published · Updated

You know a job made money when the invoice, before tax, is larger than the costs that belong on that job: burdened labor including drive, materials from the supply house and the van, equipment, subs, permits, and any callback. A deposit in checking is cash. It is not that number.

This is the check for a 5-to-15 tech HVAC, plumbing, or electrical shop on Jobber, Housecall Pro, or Workiz: what belongs on the ticket, how to read last week’s closed jobs this week, and the false positives that make a losing job look fat.

The number that answers the question

Job profit is invoiced revenue minus the costs that belong on that job. Margin is that profit divided by revenue. Gross profit on the job still has to cover shop overhead. It is not net profit, and it is not the bank balance.

Line What it is On the job?
Revenue invoiced Pre-tax total on the invoice Yes. Tax and tips are out.
Labor Clock hours, including drive, times a burdened rate Yes
Supply-house materials Parts on a PO or counter ticket Yes
Truck stock Capacitor, breaker, wax ring, fittings off the van Yes, if someone logged quantity used
Equipment Tank, condenser, panel, air handler Yes
Subs, permits, rentals Another trade, inspection, crane Yes
Callback or warranty visit Later hours and parts, no new revenue Yes, on the original job
Shop rent, dispatch, software, marketing Overhead No. Recover in the price book
Owner draw, truck loan, tax deposits Cash that leaves on its own calendar No. Not a job cost

Owners on r/Contractor put it as gross margin per job, not revenue.

What last week’s closed jobs have to show

Pull ten completed tickets from the field-service app. Fill each row from files you already have. Do not average them. A blended week hides both the drain clear and the changeout.

Check Where it lives Passes when
Invoice exists Jobber, Housecall Pro, or Workiz The job is invoiced, not just marked done
Revenue is pre-tax The invoice subtotal Sales tax is not in the profit math
Hours include drive Timesheets or the job timer Windshield time is on the job, not only roof time
Labor uses a burdened rate Tech pay record in the FSM The rate is not the paycheck wage
Supply-house bill names the job PO field, then the PDF in the inbox The address or ticket is on the invoice
Card swipe is tagged Credit card feed in QuickBooks The charge, not the statement payment, has the job
Van parts are logged Material job input or a same-day van log The capacitor did not vanish
Callbacks sit on the original $0 invoices and warranty visits Return hours and parts went back on that ticket

How to track material costs per job is the leak on parts. How to assign credit card expenses to jobs is the swipe path. A job that passes revenue and fails materials is untagged, not profitable.

A typed example

These dollars are worksheet numbers, not market rates. Replace every figure with the invoice, the timesheet, and the supplier PDF.

Line Drain clear Water-heater swap
Revenue invoiced $320.00 $4,800.00
Labor hours, including drive 1.8 6.0
Burdened rate (typed) $58.00 $58.00
Labor cost $104.40 $348.00
Supply-house materials $0.00 $1,650.00
Truck stock $12.00 $22.00
Permit $0.00 $85.00
Callbacks $0.00 $0.00
Total cost $116.40 $2,105.00
Gross profit $203.60 $2,695.00
Margin 63.6% 56.1%

1.8 × $58 = $104.40. $104.40 + $12 = $116.40. $320 − $116.40 = $203.60. $203.60 ÷ $320 = 63.6%.

6 × $58 = $348. $348 + $1,650 + $22 + $85 = $2,105. $4,800 − $2,105 = $2,695. $2,695 ÷ $4,800 = 56.1%.

A Saturday callback on the swap still belongs on that job. Add 1.5 hours and a $45 part: labor becomes $435, total cost $2,237, gross profit $2,563, margin 53.4%. Cost each tech at that tech’s rate. Do not blend $58 and $44 into $51.

When the job looks profitable and was not

The formula is honest. The inputs often are not.

Wage-only labor. Cost the swap at $28 an hour instead of $58 and labor drops from $348 to $168. Margin jumps to 59.9% while payroll tax, workers’ compensation, and the van never hit the ticket. How to calculate the fully burdened labor rate is that sheet.

Materials that never landed. Skip the tank and the swap shows $4,800 against $455 of labor, van parts, and a permit: a 90.5% bar. The tank already left on the card. HVAC owners on r/smallbusiness describe capacitors and refrigerant going through the vans while half of it never shows on the invoice.

Callbacks left on a $0 job. The original ticket keeps its profit. The return visit costs a tech hour, a part, and a truck roll and bills nothing. Pull last week’s $0 invoices and put those hours and parts back on the original.

An unpaid invoice. The job can show profit the day you close it. Checking is still waiting. Why plumbing jobs look profitable but there is no money at month end is that split: some of it is timing, some of it means the job was never that fat.

Overhead dumped onto the ticket, or left with nowhere to go. Shop rent is not a job cost. Recover it in the price book. If every job “made money” and the company still lost the month, the jobs did not cover overhead. That is pricing or volume, not tagging.

Where the field-service report actually counts

The in-app bar is a real number when the data is on the job. It is a quote when the costs never arrived.

Place What it subtracts When it is honest
Jobber profit bar Timesheets, unit costs, logged expenses Grow or Plus, per Jobber’s help updated 2026-11-12. Pricing, read 2026-11-14: Grow $149/mo billed annually for 1 user, $229 for 5 users. Plus $399/mo billed annually for 5 users. Extra users $29/mo. Truck stock still needs a quantity used. Double-counting a line item and the same expense is a known limit.
Housecall Pro job costing Fully loaded labor including travel, materials, commissions, miscellaneous Toggle on under Settings, Jobs, Costs & Materials (help updated 2026-07-22). Empty unit cost reports as pure margin. Pricing, read 2026-11-14, is a questionnaire. Max showed $299/mo billed annually, $329 monthly, or $99/mo for 3 months that day (8 users, then $35 each). LLM info (updated 2026-09-10, prices as of July 2026): job costing on Basic at $59/mo billed annually ($79 monthly, 1 user). Confirm the quote, including any Mechanical Package.
Workiz sales report Labor cost per hour times time logged, plus parts and commissions The tech’s hourly cost is saved. Updating it does not rewrite past jobs. Pricing, read 2026-11-14: request-a-quote. QuickBooks Online sync on Standard, Pro, and Ultimate.
QuickBooks project overview Income and costs tagged to that project One project per job. Job costing in QuickBooks Online is the setup. An FSM dump onto one customer leaves it empty. Pricing, read 2026-11-14: Plus $140/mo list with project profitability, Advanced $340/mo list. 50 percent off for 3 months that day.
ServiceTitan job costing Labor burden, materials, equipment, POs, commissions Deepest in-app view. The office still has to receive POs and run the report. Pricing, read 2026-11-14: quote-only, per technician. No list price.
Spreadsheet Whatever you typed Honest when every receipt made it. The HVAC template is the column list. It breaks on Friday-night re-keying.

Prices are USD from each vendor’s own page, read 2026-11-14. Housecall Pro Essentials, on that same LLM info page, is $149 a month billed annually ($189 monthly, 5 users).

Does Jobber have job costing? and Housecall Pro reports are the click paths. ServiceTitan wins the rows for shops that already live in it. Jobber and Housecall Pro win the in-app view on the FSM you already pay for, when the tags are there.

Software that matches card swipes, supply-house bills, timecards, and sub invoices to a job from the field-service app can fill the hole where the bar never got the receipt. We make Truceipts, which does this, so weigh that suggestion accordingly.

How to tell this week

You know the answer is real when last week’s closed jobs show supply-house bills and van parts, drive is in the hours, labor is burdened, and a $0 callback sits on the original row. If a job shows revenue and almost no cost, the feature is on and the inputs are not.

Pull last week’s ten closed jobs from Jobber, Housecall Pro, or Workiz. Lay each one next to the timesheets, the supplier PDFs, the card charges, and what came off the van. Those files already exist. Start there.

Frequently asked questions

Is the profit bar in Jobber or Housecall Pro enough to know if a job made money?

Only when timesheets, unit costs, and expenses actually sit on the job. Jobber's Grow and Plus profit bar subtracts those three from pre-tax revenue. Jobber's pricing page, read 2026-11-14, lists Grow at $149 a month billed annually for 1 user, or $229 for 5 users. Housecall Pro multiplies a fully loaded rate by time on the job, including travel. Empty unit costs or a van part that never logged still leave a fat bar.

Should I cost labor at the technician's wage or a burdened rate?

A burdened rate. Wage-only labor leaves payroll tax, workers' compensation, benefits, and that tech's van off the job, so every ticket looks fatter than it was. Multiply clock hours, including drive, by the rate from the fully burdened labor sheet. Two techs on one call get two rates.

Does an unpaid invoice mean the job still made money?

On accrual books, unpaid work can still show as job profit. The bank does not have it. Intuit's accounts-receivable guide, dated 2026-08-06, defines AR as money customers owe for work already delivered. Pull last week's closed jobs next to unpaid invoices. Profit on paper and cash in checking are different clocks.

Should shop rent and dispatch sit on each job to know if it made money?

No. Shop rent, the CSR, software, and marketing are overhead. Recover them in the price book by holding a gross-margin target. The tech's truck, fuel, and tools already sit in the burdened labor rate. Dumping rent onto every ticket makes long jobs look worse for a reason that has nothing to do with that ticket.

What if a closed job shows revenue and almost no material cost?

The parts probably never hit the job. A tank on the card, a Ferguson PDF with a blank PO, or a capacitor off the van still cost money. Open the card feed, the supplier inbox, and the van log for that address. A 90 percent bar on a replacement is usually a missing bill, not a great job.